The Town of LaSalle is continuing the annual Mill and Pave project for 2024. This year we will be working in multiple areas throughout LaSalle, as shown below.

Section A –  Matchett Road, from Reaume Road to Legacy Grove Drive.

Work in this area includes catch basin, wheel chair ramp, curb and sidewalk repairs. A 1.2 metre wide full depth mill, from edge of pavement and surface milling to centreline of roadway. Full depth milling to be 90mm and a surface mill of 40mm. Paving will be 50mm base asphalt and 40mm of surface asphalt. 

 Please refer to Map A for the location of work.

Section B –  Mayfair Avenue, Sacred Heart Drive, Delaware Avenue, and Gilbert Avenue.

Work includes catch basin, wheel chair ramp, curb and sidewalk repairs and a 40mm surface mill and pave of the roadway.

The roads included are:

Mayfair Avenue: from Maple Avenue to the south Cul-De-Sac.
Delaware Avenue: from Alfred Avenue to Gilbert Avenue.
Sacred Heart Drive: from Alfred Avenue to Gilbert Avenue. 

Please refer to Map B for the location of work.

Section C – Menomine Street, Superior Street, Marquette Street, Huron Street, and Lafferty Avenue.

Work includes catch basin, wheel chair ramp, curb repairs and a 40mm surface mill and pave of the roadway.

The roads included are:

Paving machine and crewMarquette Street: from Laurier Drive to Lafferty Avenue and Huron Street to Superior Street.
Menomine Street: from Lafferty Avenue to Huron Street and Superior Street to Bouffard Road.
Lafferty Avenue: from Marquette Street to the east Cul-De-Sac.
Huron Street: from Marquette Street to Matchett Road.
Superior Street: Marquette Street to the east Cul-De-Sac.

Please refer to Map C for the location of work.

 