Vince Marcotte Pedestrian Bridge Rehabilitation (Pirate Bridge)

Additional information: November, 2024 - The pedestrian bridge was recently inspected and deemed unsafe for public use. At that time the decision was made to immediately close the bridge. Some repairs can be carried out during the winter, while the remaining work will need to wait for warmer weather in the spring. We will provide an update here and on social media once the bridge is ready to be re-opened. We thank you for your patience during the closure and repair process.

The current rehabilitation and upgrades that are being constructed are weather dependent, please note that the work being carried out requires calm days, that are above zero degrees celsius.

Detour Route

Vince Marcotte Pedestrian Bridge Rehabilitation

Detour Route

Old Decking

Vince Marcotte Pedestrian Bridge Rehabilitation

Old Decking

New decking

Vince Marcotte Pedestrian Bridge Rehabilitation

New decking

  • November 29, 2024 - The pedestrian bridge (Pirate Bridge) between Vince Marcotte Park and Stanton Park is closed for maintenance and will remain closed until Spring 2025. 
    • Closure signs and detour routes will be posted. The detour route is Minto Avenue to Matchett Road, over Turkey Creek to re-connect with the LaSalle Trail.
  • January 27,2025 - Warkentin Fabricating has started construction on the The pedestrian bridge (Pirate Bridge).
  • January 28, 2025 - The pedestrian bridge (Pirate Bridge) between Vince Marcotte Park and Stanton Park is closed for maintenance and will remain closed until Spring 2025.
    • Closure signs and detour routes will be posted. Please be advised that the detour route has changed from Minto Avenue to Sprucewood Avenue. This change is being implemented as the Matchett Road Bridge over Turkey Creek is undergoing upgrades. Please see the New Vince Marcotte Pedestrian Detour Route.
  • February 5, 2025 - Suspension cables have been repaired and tightened.
  • March 11, 2025 - Concrete repairs have been completed.
  • April 4, 2025 - Metal surfaces have been sandblasted, wood surfaces have been sanded. Metal coatings have been applied.
  • April 9, 2025 - Wood decking has been completed.

Questions or Concerns:

We understand that construction work can be disruptive, and the Town of LaSalle aims to complete the project as efficiently as possible while ensuring the quality and safety of the bridge for all users. If you have any questions or concerns regarding the construction project, please feel free to contact the Town of LaSalle’s Public Works Department at 519-979-7770 or by email at publicworks@lasalle.ca.

We appreciate your cooperation and patience throughout the construction process. 

Contact Us

Town of LaSalle
5950 Malden Road
LaSalle, ON N9H 1S4
T. 519-969-7770
F. 519-969-4469
Map this Location

This website uses cookies to enhance usability and provide you with a more personal experience. By using this website, you agree to our use of cookies as explained in our Privacy Policy.